San Diego's City Auditor found that approximately $155 million in contract alterations (42% of those reviewed) were presented to Council in an untimely manner, retroactively, or not at all.$155M
review-facts-c: wording per audit exhibit
1 source
www.sandiego.govDocumentcontract modifications, representing $155 million, were not properly brought to Council for approval
Stories about San Diego Office of the City Auditor
City of San Diego · Misused public funds
San Diego auditors found the city improperly increased contract spending by $155 million over six years without required Council approval, and a year later still couldn't determine who authorized a $6.7 million overrun on a single rental contract